Kathmandu; The construction of the 28 km long Chilime-Trishuli 220 kV transmission line was started over six years ago, but only 11 km of the wire has been laid so far showing the cause of the geographical difficulty.
Targeting to evacuate electricity produced by the hydropower projects to be dev...}
Kathmandu : Nepal Electricity Authority (NEA) has set mid-January 2024 as the deadline for completion of the construction of the 220 kV Chilime-Trishuli transmission line and substations.
The Chilime-Trishuli transmission line project is aimed at supplying electricity to the hydropower projects b...}
About 60 per cent works on the Chilime-Trishuli 220 kV transmission line and substations under construction in Rasuwa and Nuwakot districts have been completed.
Work is moving in full swing to complete the construction of the transmission line within August 2022, according to Nepal Electric...}