Energy Update

  • NEA : 9128 MWh
  • Subsidiary Company : 3418 MWh
  • Private Sector : 11795 MWh
  • Import : 12741 MWh
  • Tripping : 3185 MWh
  • Energy Demand : 40267 MWh
  • NEA : 0 MW
  • Subsidiary Company : 0 MW
  • Private Sector : 0 MW
  • Import : 0 MW
  • Tripping : 0 MW
  • Peak Demand : 1970 MW
2024 May 3,Friday
×

Kathmandu : Nepal Electricity Authority (NEA) has set mid-January 2024 as the deadline for completion of the construction of the 220 kV Chilime-Trishuli transmission line and substations.

The Chilime-Trishuli transmission line project is aimed at supplying electricity to the hydropower projects both under construction and planned along the Trishuli River and its tributaries. Under the project, 220/132/33 KV Chilime Hub and Trishuli 3B Hub substations are under construction at Thambuche in Amachodingmo Rural Municipality of Rasuwa and Pahirebesi in Kispang Rural Municipality of Nuwakot respectively. Also, Chilime-Trishuli 3B hub 28 km 220 kV double circuit transmission line is being constructed.

A high-level team led by the NEA Managing Director Kulman Ghising and Deputy Executive Director of Broadcasting Directorate Dirghayu Kumar Shrestha, during an on-site monitoring of the substations and transmission lines under construction on Saturday and Sunday, set the deadline for project completion. The team fixed the timeline after holding discussions with the project management, consultants, and the contractor company.

NEA Managing Director Ghising said lacking transmission lines, the 111 megawatt Rasuwagadhi and 42.5 megawatt Sanjen hydroelectric projects under construction by Chilime Hydro Electricity Company should be taken seriously to prevent power leakage. The final phase of both projects is being done with the goal of producing electricity in the next four months.

"The electricity produced by the two projects will help a lot in managing the electricity demand in the upcoming winter season. If there is a situation where electricity cannot be connected due to the lack of transmission lines, the state will suffer a huge loss. Let us all be serious and sensitive in this regard," Ghising said.

The transmission line construction has faced several challenges due to the difficult geographical terrain, lack of roads, problems in the transportation of construction materials, poor performance by contractors, land use issues in forest areas, and local obstacles, compounded by the impact of the COVID-19 pandemic.

In the last two years, the Chinese company Pinggao Group of Companies, the contractor of the project, has achieved some improvements in its performance. The company has promised to complete the project by mid-January next year.

The civil construction work, which includes housing the main equipment of both substations, is in its final stages. All essential equipment, including power transformers and GIS units, have been transported to the project site. Furthermore, all the equipment required for the transmission line, such as towers and conductors, has been supplied to the construction site.

The foundations of 56 of the 76 towers on the total 28 km transmission line have been laid. The foundation of the rest of the towers is being laid. As many as 48 towers have been erected so far. The overall construction progress of the project is 90 percent.

The Chilime-Trishuli 3B hub transmission line includes a 20 km double-circuit line in the Chilime-Mailung section and an 8 km four-circuit line extending to the Mailung-Trishuli 3B hub. Korean companies are leading the construction of a multi-circuit line to connect the power generated by the 216 MW Upper Trishuli-1 Hydroelectric Project, with 60 percent of the construction cost being covered by Upper Trishuli-1.

A contract was signed with Pinggao in November 2017 for the construction of the transmission lines and substations. The contract agreement was put to force in January 2018. The estimated cost of the project is 30.9 million US dollars that involves investments from the Nepal government, NEA, and concessional loans from the German Development Bank and the European Investment Bank.

Conversation

  • Info. Dept. Reg. No. : 254/073/74
  • Telephone : +९७७-१-५३२१३०३
  • Email : [email protected]
© 2024 Urja Khabar. All rights reserved
Contact for advertisement +९७७-१-५३२१३०३
Design By : Nectar Digit