Kathmandu: The 285 MW Upper Tamor Hydropower Project, promoted by Tamor Energy Ltd. (TEL), is set to become Nepal’s first hydropower project to use Tunnel Boring Machine (TBM) technology for the construction of its 8.7 km headrace tunnel.
On Thursday (April 3), TEL signed an agreement...}
Kathmandu: Upper Tamor 'A' Hydropower Project has finalized its Environmental Impact Assessment (EIA).
According to Union Hydropower Limited, the developer of the Upper Tamor ‘A’, it has recently submitted its EIA report at the Department of Environment for final approval...}
Electricity generated from the Upper Tamor Hydroelectricity Project in Taplejung district will soon be connected to 220 KV transmission line. The energy will be evacuated via 220KV transmission line which is being constructed by the Nepal Electricity Authority in Dhungesanghu of the district. ...}