विद्युत अपडेट

  • प्राधिकरण : ९१२८ मे.वा.घन्टा
  • सहायक कम्पनी : ३४१८ मे.वा.घन्टा
  • निजी क्षेत्र : ११७९५ मे.वा.घन्टा
  • आयात : १२७४१ मे.वा.घन्टा
  • निर्यात : मे.वा.घन्टा
  • ट्रिपिङ : ३१८५ मे.वा.घन्टा
  • ऊर्जा माग : ४०२६७ मे.वा.घन्टा
  • प्राधिकरण : मे.वा.
  • सहायक कम्पनी : मे.वा.
  • निजी क्षेत्र : मे.वा.
  • आयात : मे.वा.
  • निर्यात : मे.वा.
  • ट्रिपिङ : मे.वा.
  • उच्च माग : १९७० मे.वा.
२०८१ ब‌ैशाख २१, शुक्रबार
×
जलविद्युत सोलार वायु बायोग्यास पेट्रोलियम अन्तर्राष्ट्रिय ई-पेपर जलवायु ऊर्जा दक्षता उहिलेकाे खबर ईभी सम्पादकीय बैंक पर्यटन भिडियो छापा खोज प्रोफाइल ऊर्जा विशेष ऊर्जा

Kathmandu: The 220 kV Udipur-Markichok-Bharatpur transmission line, which was supposed to come online three years ago has not been completed yet.

According to the project, it has taken almost six years now for the installation of the transmission line. Narayan Regmi, divisional head of the project said only about 65 percent of the work has been completed till date. According to him, they have extended the timeline three times due to the slow work progress of the contractor.

The contract for the construction of the transmission line was signed in January 2018. The slow work progress has been attributed to the delay in cutting down the trees that fall under the alignment of the transmission line.  

Regmi said the new deadline has been set for the coming June. According to the project, 193 towers have to be built to carry this transmission line in a distance of 67 km stretch from Udipur in Lamjung to Bharatpur in Chitwan. A total of 45 towers will be built in Lamjung. As of now, 25 towers in Lamjung have been constructed.

This transmission line will complement in six kilometers to bring the electricity of the Dordi Corridor project to the switchyard of the medium current hydropower plant. Seven towers have already been constructed in the six km section of Madhya Marsyangdi section starting from Udipur.

The foundation of 15 towers has been completed in Tanahun, while the foundation of one tower has been laid in Chitwan. Similarly, the foundation structure of the tower in Gorkha has been built.

प्रतिक्रिया दिनुहोस

© 2024 Urja Khabar. All rights reserved
विज्ञापनको लागि सम्पर्क +९७७-१-५३२१३०३
Site By : Nectar Digit